DYK, Circuit Judge.
Todd Construction, L.P. ("Todd") is a government contractor. Todd filed suit in the Court of Federal Claims ("Claims Court") under the Tucker Act, 28 U.S.C. § 1491, and the Contract Disputes Act ("CDA"), 41 U.S.C. § 601 et seq., alleging that the United States Army Corps of Engineers (the "government") gave it an unfair and inaccurate performance evaluation. The Claims Court held that the CDA provided it with subject matter jurisdiction over such a claim, but dismissed Todd's complaint for lack of standing and failure to state a claim. Todd Constr., L.P. v. United States, 85 Fed.Cl. 34 (2008) ("Todd I"); Todd Constr. L.P. v. United States, 88 Fed.Cl. 235 (2009) ("Todd II"); Todd Constr. L.P. v. United States, 94 Fed.Cl. 100 (2010) ("Todd III"). We affirm both the Claims Court's determination that it had jurisdiction under the CDA and its dismissal of Todd's complaint on the grounds of lack of standing and failure to state a claim.
In 2003, Todd entered into two task order contracts with the government on two construction projects for roof repairs of government buildings. The parties refer to these projects as "Building 2121" and "Building 3611." The government agreed to amended completion dates, making the completion dates June 25, 2004, for the Building 2121 project and July 30, 2004, for the Building 3611 project. Due to a series of delays (some of which Todd alleges were caused by its subcontractors, the government, or other circumstances outside of its control), the projects were not completed and accepted by the government until September 30, 2005, and October 14, 2005, respectively.
At the time, the Federal Acquisition Regulations ("FAR") required that for "each construction contract" for "$550,000 or more," a "[performance] report shall be prepared ... in accordance with agency procedures" and that "[e]ach performance report shall be reviewed to ensure that it is accurate and fair."
Todd received negative interim performance evaluations from the resident engineer for both projects on February 5, 2004. On March 26, 2006, the resident engineer issued his proposed negative final performance evaluations for both projects pursuant to 48 C.F.R. § 36.201 and ER 415-1-17. On April 20, 2006, Todd submitted comments protesting the proposed evaluations. These comments primarily took issue with the purported lack of timeliness of its performance, asserting that its subcontractors and "other problems" that were "beyond Todd's control" caused the delays. J.A. 41-43. Todd also asserted that it "took extraordinary steps to supervise, manage, coordinate and control its subcontractors," that it was "responsive to the Government's concerns," and that its "quality control system" was adequate. Id. The evaluations were not changed as a result of Todd's comments.
In the final performance evaluations, the resident engineer assigned Todd an overall performance rating of unsatisfactory. The resident engineer also assigned unsatisfactory ratings for each project in fifteen individual performance categories. Many of these categories (e.g., "adherence to approved schedule," "correction of deficient work in a timely manner," and "resolution of delays") related to the timeliness of Todd's performance. J.A. 35. Todd was also given unsatisfactory ratings in categories such as "coordination and control of subcontractor[s]," "quality of workmanship," "management of resources/personnel," and "cooperation and responsiveness." Id. The resident engineer also included specific comments expanding on the negative ratings. For example, the resident engineer stated that "[the] [f]irst submittal was not received until 22 Dec 03," that the "[c]ontractor did not start work until the week of 29 March 04," and that the "[c]ontractor's quality control system allowed subcontractors to field paint damaged roof panels without government approval." Id.
Following internal reviews within the Department of the Army, the final evaluations were issued on July 23, 2006. Todd sought review by the contracting officer. On April 25, 2007, the contracting officer issued a "final decision regarding [Todd's] performance," concluding that "the [u]nsatisfactory performance appraisal [was] justified and all required procedures were followed." J.A. 59.
On May 25, 2007, Todd filed a complaint in the Claims Court, alleging that the government failed to follow the proper procedures and that the unsatisfactory performance evaluations were arbitrary and capricious and seeking, inter alia, a declaratory judgment. In this complaint, Todd did not challenge any particular performance ratings. Instead, it merely pled
On August 14, 2009, Todd filed its amended complaint as permitted by the Claims Court. Although Todd added a series of factual allegations, it again did not specifically identify which unsatisfactory ratings were arbitrary and capricious. The complaint appeared to challenge primarily the unsatisfactory ratings related to Todd's timeliness of performance.
In its third and final opinion, the Claims Court reaffirmed that it had subject matter jurisdiction over Todd's complaint. See Todd III, 94 Fed.Cl. at 107-12. However, the Claims Court also held that Todd lacked standing to sue for the alleged procedural violations because "there [was] no discernible injury to the plaintiff from the error." Id. at 113. With respect to Todd's claim that the performance evaluation was unfair and inaccurate, the Claims Court held that Todd did have standing. Id. at 107-112. However, the court held that Todd failed to state a claim under Rule 12(b)(6) because Todd was responsible for the acts of its subcontractors as a matter of law and "there [was] nothing in the amended complaint beyond Todd's bare assertion of non-responsibility to support any conclusion that assigning `unsatisfactory ratings' was an abuse of discretion." Id. at 115.
Todd timely appealed to this court, and we have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).
We review de novo the Claims Court's determination that it had subject matter jurisdiction, its dismissal of a complaint on the grounds of standing, and its dismissal for failure to state a claim under Rule 12(b)(6). M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323, 1327 (Fed.Cir.2010); Bank of Guam v. United States, 578 F.3d 1318, 1325 (Fed.Cir.2009).
We first consider the government's contention that the Claims Court lacked
Congress' overall purpose to confer comprehensive jurisdiction under the CDA confirms that we should read the definition of "claim" broadly. We have previously recognized that "[i]n defining the jurisdiction of the [Claims Court] over CDA disputes, Congress has chosen expansive, not restrictive, language." Alliant Techsystems, Inc. v. United States, 178 F.3d 1260, 1268 (Fed.Cir.1999). The Tucker Act provides jurisdiction to "render judgment upon any claim by or against ... a contractor arising under section 10(a)(1) of the [CDA], including ... nonmonetary disputes on which a decision of the contracting officer has been issued under section 6 of the [CDA]." 28 U.S.C. § 1491(a)(2) (emphases added). In Alliant, the government argued that "nonmonetary disputes" should be read narrowly to exclude "disputes arising prior to the completion of work on a contract" and "disputes that have not yet ripened into a monetary dispute but ... could" if the contractor "could convert the claim into one for monetary relief" by its own actions. 178 F.3d at 1268 (internal quotation marks omitted). We rejected this narrow reading, emphasizing that the provision "begins by broadly granting the court jurisdiction over `any claims,'" uses the "nonrestrictive term (`including')," and ends the provision with "equally nonrestrictive language" concerning "nonmonetary disputes." Id. We also explicitly recognized that "[t]he FAR has... ensured that review of contract claims will be relatively easy to obtain, by defining the term `claim' broadly, to include a demand or assertion seeking ... relief arising under or relating to the contract." Id. at 1271. Therefore, the broad language of the statute and FAR provision supports a broad reading of the term "claim."
The legislative history of the CDA and Tucker Act also supports a broad reading of the term "claim." Both the House and Senate Reports explained that the CDA was intended to "implement[ ] recommendations of the Commission on Government Procurement." S.Rep. No. 95-1118, at 1 (1978), reprinted in 1978
Not only is the term "claim" broad in scope, the "relating to" language of the FAR regulation itself is a term of substantial breadth. The term "related" is typically defined as "associated; connected." See Random House Webster's Unabridged Dictionary 1626 (2d ed. 1998); see also Black's Law Dictionary 1288 (6th ed. 1991) (defining "related" as "[s]tanding in relation; connected; allied; akin"); Oxford English Dictionary 1695 (3d ed. 1947) (defining "relation" as "any connection, correspondence, or association, which can be conceived as naturally existing between things").
The Supreme Court has interpreted the term "related to" broadly. See, e.g., Celotex Corp. v. Edwards, 514 U.S. 300, 307-08, 115 S.Ct. 1493, 131 L.Ed.2d 403 (1995) (holding that Congress' jurisdictional grant to bankruptcy courts to hear proceedings "related to" a bankruptcy case "suggests a grant of some breadth" and includes, inter alia, suits between third parties which have an effect on the bankruptcy estate); Morales v. Trans World Airlines, Inc., 504 U.S. 374, 383-84, 112 S.Ct. 2031, 119 L.Ed.2d 157 (1992) (holding that preemption provision of Airline Deregulation Act — preempting laws "relating to rates, routes, or services" of any air carrier — should be broadly construed); Shaw v. Delta Air Lines, Inc., 463 U.S. 85, 96-97, 103 S.Ct. 2890, 77 L.Ed.2d 490 (1983) (holding that state law "relates to" an employee benefit plan and is therefore preempted by ERISA "if it has a connection with, or reference to, such a plan"). Similarly, in Tyco Healthcare Group LP v. Ethicon Endo-Surgery, 587 F.3d 1375, 1378 (Fed.Cir.2009), we recognized that "[i]n general, `related to' means one thing has some ... connection to another thing," and "[i]n legal parlance," the term has "similar breadth." We therefore interpreted the contractual phrase "related to pending litigation" broadly. Id. at 1379.
In line with this authority, we have previously held that to be a claim "relating to the contract" under the CDA, the claim "must have some relationship to the terms or performance of a government contract." Applied Cos. v. United States, 144 F.3d 1470, 1478 (Fed.Cir.1998).
BLR Grp. of Am., Inc. v. United States, 94 Fed.Cl. 354, 373 (2010) (quoting Todd I, 85 Fed.Cl. at 44-45).
The government does not contend that the contracting officer's decision regarding the negative performance evaluations bore no relationship to Todd's performance under the contract. Rather, relying on Paragon Energy Corp. v. United States, 645 F.2d 966 (Ct.Cl.1981), the government argues that Todd's claim cannot "relat[e] to the contract" unless it is based on a "valid contractual theory," (e.g., breach of contract or mistake). Paragon imposes no such limitation. While as a general matter Paragon found that the CDA statute "should not be interpreted quite so broadly as its language at first blush would suggest," it recognized that the "language is obviously quite broad." Id. at 971. It found that a narrower interpretation was required only in one respect — the term "claim" should not be interpreted to include a challenge that the legislative history showed Congress intended to exclude. Id. at 973-75.
Specifically, the Court of Claims held that a challenge to the government's denial of a request for contract modification under Public Law 85-804 was not a "claim" under the CDA. Id. at 972. Public Law 85-804 gave government agencies the discretionary authority to modify contracts if the modifications would facilitate the national defense. Id. at 968. Congress was concerned that a bill which granted CDA jurisdiction over Public Law 85-804 challenges would allow "agencies to settle claims independent of their legal or contractual merits," i.e. "horse trade settlements", which could only be done "through resort to Public Law 85-804 with its [attendant] safeguards including congressional review." Paragon, 645 F.2d at 973 (quoting S. Rep. No. 95-1118, at 5). Therefore, Congress passed a final version of the bill that "address[ed] the concerns expressed by [several Senate committees] that the Act not permit the Contracting Officer or the Agency Boards to grant the discretionary relief ... authorized by Public Law 85-804." Id. at 974 (quoting 124 Cong. Rec. 18639-41 (daily ed. Oct. 12, 1978)).
In Paragon, while holding that the Public Law 85-804 claim was not within the scope of the CDA, the court also held that the CDA did confer jurisdiction over the contractor's claim for a contract reformation. Id. at 972, 975. The court concluded that "Congress could not have expressed itself more clearly to the effect that all contractor claims based upon a valid contractual theory fall within [its] jurisdiction under the [CDA]." Id. at 975. Contrary to the government's contention, Paragon merely confirms that all claims which are
Lastly, the government asserts that even if performance evaluations "relat[e] to the contract" under the CDA, the performance evaluation regulations cannot provide Todd with a cause of action because they "[exist] primarily for the benefit of the [g]overnment." Appellee's Br. 42. The government relies on our decisions in Freightliner Corp. v. Caldera, 225 F.3d 1361, 1365 (Fed.Cir.2000), Cessna Aircraft Co. v. Dalton, 126 F.3d 1442, 1451 (Fed.Cir.1997), and Rough Diamond Co. v. United States, 351 F.2d 636, 640-42 (Ct.Cl. 1965), in which we held that particular plaintiffs could not sue under a statute or regulation if the law was not intended to benefit that class of plaintiffs. See also United States v. N.Y. & Porto Rico S.S. Co., 239 U.S. 88, 36 S.Ct. 41, 60 L.Ed. 161 (1915). Those cases established that a law or regulation must "protect or benefit a class of persons in order for that class to be able to bring suit against the government" and that the class must be more than an "incidental beneficiary" of the regulation. Cessna Aircraft, 126 F.3d at 1451-52. However, it is possible for a regulation or law to benefit both the government and a class of private parties. See Rough Diamond, 351 F.2d at 640. That is the case with performance evaluations.
48 C.F.R. § 42.1502 is the current regulation providing for mandatory performance evaluations under certain government contracts, including construction contracts. Subpart 42.15 of the FAR was added in 1995 to "implement[] Office of Federal Procurement Policy Letter 92-5." 48 C.F.R. § 42.1500 (1996). In that letter, the Office of Federal Procurement Policy explained that "policies and procedures for collecting, recording, and using past performance information [which many agencies have already established] ... are extremely important to both the Government and to contractors, and requirements are necessary to help ensure their integrity and fairness." Past Performance Information, 58 Fed. Reg. 3,573-02, 3,575 (Jan. 11, 1993) (emphasis added). As this history
The government argues that we should nonetheless dismiss Todd's complaint for lack of standing (with respect to its procedural allegations) and failure to state a claim (with respect to its substantive allegations).
As explained above, Todd alleged that the government failed to follow four procedural requirements listed in ER 415-1-7. These were notifying Todd of the performance elements that would be used to evaluate it; holding a conference with Todd before issuing an interim unsatisfactory performance rating; re-evaluating the interim unsatisfactory rating every three months; and issuing of a final evaluation within sixty days after project completion. In general, standing requires that the plaintiff show an injury in fact, "a casual connection between the injury and the conduct complained of," and that his injury would likely be redressable by court action. Lujan v. Defenders of Wildlife, 504 U.S. 555, 560, 112 S.Ct. 2130, 119 L.Ed.2d 351 (1992). However, the Supreme Court has also explained that a "person who has been accorded a procedural right to protect his concrete interests can assert that right without meeting all the normal standards for redressability and immediacy." Id. at 573 n. 7, 112 S.Ct. 2130. Some courts of appeals have accordingly relaxed the causation requirement when determining standing for procedural injuries, finding it satisfied when following the correct procedures plausibly may have changed the result. See, e.g., Ctr. for Food Safety v. Vilsack, 636 F.3d 1166, 1172 (9th Cir.2011); Friends of Tims Ford v. TVA, 585 F.3d 955, 968 (6th Cir.2009); Pub. Citizen v. U.S. Dep't of Justice, 491 U.S. 440, 444-49, 109 S.Ct. 2558, 105 L.Ed.2d 377 (1989).
These relaxed standards have been applied, however, in cases involving fundamental procedural rights, such as the right to a hearing, see Lujan, 504 U.S. at 572, 573 n. 7, 112 S.Ct. 2130, the right to an environmental impact statement, Ctr. for Food Safety, 636 F.3d at 1172, and the right to have a decisionmaker free from ex parte contacts in formal administrative hearings, Elec. Power Supply Ass'n v. FERC, 391 F.3d 1255, 1262 (D.C.Cir. 2004).
In fact, Todd has alleged nothing to indicate that the outcome of the performance evaluations would have been any different if the purported procedural errors had not occurred. Todd did not allege that government compliance with its procedural standards would have changed its actions. Although Todd alleged it was not provided "an opportunity to cure any perceived deficiencies in its performance," J.A. 109, Todd did not allege that if the required procedures had been followed, it would have taken curative action or that the performance evaluation would have been different. Therefore, Todd lacks standing to sue with respect to the procedural violations.
Todd clearly does have standing to sue based on its substantive allegation that the government acted arbitrarily and capriciously in assigning an inaccurate and unfair performance evaluation. However, the government contends that Todd failed to state a claim entitling it to relief. We must dismiss a complaint for failure to state a claim where the complaint does not "state a claim to relief that is plausible on its face," i.e., where the plaintiff fails to "plead[ ] factual content that allows [a] court to draw the reasonable inference that the defendant is liable for the misconduct alleged." Ashcroft v. Iqbal, 556 U.S. 662, 129 S.Ct. 1937, 1949, 173 L.Ed.2d 868 (2009). Here, Todd must plead facts which give rise to a plausible inference that the government abused its discretion in awarding the negative performance ratings.
The government argues that Todd failed to meet this burden because it failed to "allege that the performance evaluations at issue ... were based solely — or even substantially — upon the specific performance difficulties" that Todd claimed were not its fault. Appellee's Br. 56-57. Comparing the factual allegations in the complaint with the performance evaluations, we conclude that the government is correct. All of the facts alleged by Todd could be true and yet it does not follow that any of the unsatisfactory ratings were an abuse of discretion or should be changed.
Todd's complaint raised issues related to the timeliness of its performance (e.g., "adequacy of initial progress schedule," "adherence to approved schedule," "submission of required documentation," and "resolution of delays"). J.A. 114. In this respect, Todd merely alleged that the "delays... were caused by unforeseen events, many of which were neither the fault nor the responsibility of Todd." Id. at 113 (emphasis added). Although Todd alleged that numerous specific delays were not Todd's responsibility, those allegations cannot change the fact that Todd admits in its appeal brief that some delays were not the government's fault but were instead caused by Todd's subcontractors. We have previously explained that "a contractor is responsible for the unexcused performance failures of its subcontractors." See, e.g., Johnson Mgm't Grp. CFC, Inc. v. Martinez, 308 F.3d 1245, 1252 (Fed.Cir. 2002). Todd has failed to allege facts that would excuse its subcontractors' delays. Todd's bare assertion that it is not responsible for the actions of its subcontractors is a legal conclusion, and we are not required to assume that legal conclusions are true. See Iqbal, 129 S.Ct. at 1949-50. Todd also specifically admitted in the complaint that it delivered only "the majority [i.e., not all] of the [required] submittals" to the government on time. J.A. 107, 110. The performance evaluations do not specify how much delay the government attributed to Todd; they simply indicate that Todd's performance was untimely. To raise a plausible inference that the ratings were
No costs.